Phase 1-A: Foundation slab of 22,000 sq.ft. – COMPLETED

Phase 1-B: Site utilities & fire lane – to be completed by July 2022, inShaAllah – IN PROGRESS

Phase 1-C: Parking lot – To be decided in next few weeks

Phase 2: The shell and finish out for retail/office space and 28 apartments – Expected completion June 2023.